Completion of Warehouse Refurbishment

Completion of Warehouse Refurbishment

The Fire Damaged Warehouse that we’ve been working on in Great Yarmouth is now ready for a new future. The team completed their final tasks on site last week and the project has since been signed off by the client.

Since the last update a month ago, our work has involved a last push to finish the construction of the previously fire damaged offices.  In addition to building new walls, the team spent a lot of time plastering and painting.  We then laid flooring in both the offices and warehouse areas.  We also fitted out the toilet facilities and kitchenette.  While all of this was taking place, electrical and plumbing works were completed, and we installed new drains outside.

The result is a smart, clean, fully functioning warehouse and office space.  All it needs now is the arrival of its new tenants!